CAG audit reveals water supply challenges in Military Engineer Services

A recent Comptroller and Auditor General (CAG) report on defence covering 20 GEs from 2018-19 to 2020-21 highlights gaps in supply, infrastructure, and operational efficiency.

| Updated: 25 December, 2024 4:12 pm IST
Indian MES faces challenges in managing water supply to defence installations.
Indian MES faces challenges in managing water supply to defence installations.

NEW DELHI: The Comptroller and Auditor General (CAG) report on defence covering the period from 2018-19 to 2020-21 reveals that 15 out of 20 Garrison Engineers (GEs) supplied less water than authorized, with shortages ranging from 10.13% to 62.97% of the prescribed quantity. Agreements with external water utilities, intended to bridge the water supply gap, were largely ineffective, as 12 out of 13 GEs received less than the agreed quantities.

 

Report of the Comptroller and Auditor General of India on UnionGovernment (Defence Services-Army) presented in Parliament: Indian Military Engineer Services faces challenges in managing water supply.
Report of the Comptroller and Auditor General of India on Union
Government (Defence Services-Army) presented in Parliament: Indian Military Engineer Services faces challenges in managing water supply.

 

The Military Engineer Services (MES), responsible for managing water supply to defence stations, cantonments, and installations, is facing significant challenges in ensuring adequate and efficient water distribution. A recent audit covering 20 GEs from 2018-19 to 2020-21 highlights gaps in supply, infrastructure, and operational efficiency.

 

ALSO READ: CAG audit exposes 97% shortfall, mismanagement in raising porter companies under Eastern Command

 

Despite directives issued in November 2018 to automate water supply management, 16 GEs had yet to implement the system, hampering operational efficiency and monitoring of water usage.

 

The audit revealed that over 14,940 lakh gallons of water were lost to leakage, resulting in a financial loss of ₹11.53 crore during the audit period. This highlights the need for better infrastructure maintenance and water conservation practices.

 

Of the 10 water augmentation projects under the Annual Major Works Programme (AMWP), only four were completed. Five projects were left incomplete, and one had not started, further exacerbating the supply issues.

 

ALSO READ: CAG Report on Defence: 13th Plan for RVS did not include capability development, modernisation

 

The audit also found non-compliance with Bureau of Indian Standards (BIS) for drinking water quality. Overhead tanks and reservoirs were not cleaned as per prescribed schedules, and essential water decontamination equipment remained non-functional, putting the quality of water at risk.

 

18 GEs reported fund allocations that were 13.80% to 47.67% less than their demands for water supply maintenance. This funding shortfall has impacted the ability to address infrastructure issues and ensure reliable water supply.

 

The MES must address these systemic issues to ensure uninterrupted and quality water supply for defence installations, which is critical for operational readiness and personnel welfare.

Also Read Story

Chokli strikes again: Kohli’s latest drama with Konstas sparks outrage

Ponting pushed, elbowed Harbhajan in 1998 what Kohli did to Konsas; Fans recall

Katra erupts in protests over Ropeway Project

Fans stand by Virat Kohli amid on-field altercation with Konstas